The Leisure Media Company Ltd
The Leisure Media Company Ltd
The Leisure Media Company Ltd
Leisure Opportunities
Job search
Job Search
see all jobs
Latest job opportunities
Exeter City Council
£40,221 - £42,403pa + pension + benefits
Exeter
Harrow School
£13.71 per hour
Harrow, London
Mount Batten Group
c£65,000pa + pension + benefits
mount batten centre, plymouth
The Pickaquoy Centre
£30,000pa + local Govt pension + attractive benefits package
Orkney, Scotland
Active Luton
£61,000 - £64,000 + exceptional pension + excellent benefits
Luton

The only way is up: Why building above rail lines could be the future of city building

Job opportunities
Active Luton
£61,000 - £64,000 + exceptional pension + excellent benefits
location: Luton, United Kingdom
Mount Batten Group
c£65,000pa + pension + benefits
location: mount batten centre, plymouth, United Kingdom
Exeter City Council
£40,221 - £42,403pa + pension + benefits
location: Exeter, United Kingdom
more jobs
At grade transportation corridors, such as rail or rapid bus lines, slice cities in half. Having the opportunity to build above these helps connect neighbourhoods and build vibrant communities
– Ian Washbrook, Entuitive

Elevating new buildings above existing transport infrastructure is an increasingly viable way of unlocking commercial value from previously undevelopable properties, a leading engineering consultant has told CLAD.

Ian Washbrook, associate at Entuitive, believes that innovative new technologies and engineering solutions can ensure downtown areas continue to develop even as available sites become more scarce.

The firm’s Canadian office, which Washbrook leads, is currently building Calgary’s New Central Library above the city’s LRT rail line. The half-moon shaped structure, just east of City Hall in East Village, has been designed by architecture studios Snøhetta and Dialog to resemble a modern yet graceful ship “sailing into the future.”

Work is being completed in phases so as to minimise disruption to the rail network, which will run below the new structure.

“At grade transportation corridors, such as rail or rapid bus lines, slice cities in half,” said Washbrook. “Having the opportunity to build above these helps connect neighbourhoods and build vibrant communities.

“Calgary Municipal Land Corporation (CMLC) recognised the library would be a fantastic addition to the city’s East Village, and had the vision to see this underutilised land transformed into one larger, more valuable property.

“Working with Calgary Transit on design scenarios for a tunnel extension constructed with a building above, it became clear this was a feasible approach from operations, safety, and budget perspectives. The tunnel extension comprises close to 40 per cent of the overall footprint of the New Central Library.”

Washbrook told CLAD that retail developments are among the most feasible projects to span across tracks, as noise disruptions are less problematic for shops than with other types of building, but added that “hotels, museums and theatres are also physically possible, as long as base isolation is studied by an acoustic consultant so that airborne and structure-borne vibrations are kept at a tolerable level.”

In addition to the Calgary project, Entuitive are also building a platform over New York’s Penn Station in Manhattan West – reclaiming a hectare of land and spanning 240ft over the busiest rail corridor in North America, including 15 active train lines. The site will feature a public plaza, three high-rise commercial towers and a hotel.

Meanwhile, urban planners in Toronto are considering a proposal to build a 21-acre deck park over one of the busiest sections of the city’s rail corridor.

In his own words
Ian Washbrook on the new Central Library and the potential of ‘elevated’ structures

Why was the decision made to build Calgary New Central Library above the rail line?

The library had long outgrown their existing space, and began looking for a new home with the functional spaces required by a modern day library.

The building is now under construction on a parcel of land above Calgary Transit’s Red Line rail corridor, which exits and enters a tunnel extending from Stampede Station to 9th Avenue. The tunnel was constructed in the early 1980’s to enable the LRT infrastructure to cross the CP Rail east-west rail corridor. For many years, the land surrounding the rail corridor served as underutilised surface parking lots. Two small oddly shaped wedges of property on either side of the tracks were not overly appealing for commercial or residential developers given limited size and inefficient configuration.

Entuitive performed an initial study for CMLC leveraging our experience unlocking land use opportunities above and next to transit. Entuitive’s precedent project was the Manhattan West Platform in New York City, which created an additional 2.6 acres of functional space, enabling the developer to construct a 5.4 million sq ft office development in west Manhattan.

What is innovative about this approach?

Constructing a building over an active LRT line had never been done before in Calgary and several innovative engineering solutions were employed.

We had to fast-track the encapsulation design and construction before the final design of the New Central Library building was complete. The completed encapsulation also served as a temporary construction barrier protecting the trains from construction activity above.

To speed up the process and eliminate shutdowns, we fabricated precast wall panels off-site, which enabled a one-sided form which acted as a guide for the placement of permanent encapsulation wall reinforcement. The wall panels served as safety barriers between the busy rail corridor and the construction workers.

A roof system was selected that was quick to install during a weekend shutdown. Again, precasting the roof framing double tees system saved valuable time. They were also the most cost effective precast section, and the lightest section to install. Once the encapsulation walls were cast and ready to accept the roof framing precast double tees, the installation of approximately 150 meters of roof panels only took approximately 30 hours and was scheduled over a long weekend shutdown.

Having to work within strict time restraints meant that optioneering of the library building had to be performed as the construction of the encapsulation took place. Load assumptions were made for the foundations of the encapsulation to support the load of the library building above.

We worked with the curve of the LRT tracks to inform the shape of the building. Large steel trusses were designed to span across the encapsulation, allowing for a column free main entrance which allows for the building to cantilever at the north tip, directly above of the tracks.

What were the biggest challenges?

The design and construction sequencing was intricately planned to maximize the revenue hours of the LRT line, and to minimise the number of shutdowns. Calgary Transit trains operate from roughly 5:00 AM till 1:00 AM. With approximately 1.5 hrs needed to power up and power down the system, construction workers had only a 1-2 hour window to work within the clearance envelope around the traction power overhead (OLS) line system. The innovative design allowed for most of the construction to take place outside of the highly electrified zone.

Existing soil conditions consist of 3m of fill on top of 5m of native gravel on a bedrock comprised of silt stone. Shallow spread footings would have required extensive excavation, and the risk of undermining the rail corridor. Large 4’-6’ foot diameter piles were augured into the bedrock. To achieve the adequate foundation resistance, many of the piles had to be advanced 18m into the rock.

How will the library adapt to the noise of the railway?

We were fortunate enough to work with a tenant that currently has their main branch adjacent to the LRT rail corridor. They are used to the rumble of the trains. The library was not designed to be fully acoustically isolated. Only certain quiet spaces such as reading rooms and meeting rooms were sound-proofed. The cost to isolate the entire building would have been cost prohibitive. To isolate the tracks was a non-starter given that the tracks would have had to be pulled out and new base isolators installed, which would have resulted in too much down time for an extremely busy rail corridor.

Sign up for FREE ezines & magazines
Elevating new buildings above existing transport infrastructure is an increasingly viable way of unlocking commercial value from previously undevelopable properties, a leading engineering consultant has told CLAD.
CLD,PRO,ARC,DES,DEV,TEC
THUMB15879_584615.jpg

More News

1 - 15 of 67,887
24 Apr 2024
The US spa industry is continuing its upward trajectory, achieving an unprecedented milestone with a record-breaking revenue of US$21.3 billion in 2023, surpassing the previous ... More
24 Apr 2024
Short-term incentives to exercise, such as using daily reminders, rewards or games, can lead to sustained increases in activity, according to new research. Researchers found ... More
24 Apr 2024
Spa and wellness veteran Shannon Malave has been named spa director at iconic US spa destination Mohonk Mountain House. Based in New York’s verdant Hudson ... More
23 Apr 2024
Six Senses Kyoto opens its doors today, marking the eco-luxury hotel and spa operator’s entry into Japan and a new addition to its urban collection. ... More
23 Apr 2024
With the launch of its 49th John Reed, RSG Group is looking for more opportunities for its high-end brand in the US and Europe. Cosmopolitan ... More
23 Apr 2024
PureGym saw revenues rise by 15 per cent in 2023, with the company announcing plans to develop 200 new clubs in the next three to ... More
23 Apr 2024
The UAE’s first-ever Dior Spa has officially launched at The Lana, Dubai – the Dorchester Collection’s debut property in the Middle East. Bathed in natural ... More
22 Apr 2024
The Sacred River Spa at Four Seasons Resort Bali at Sayan will reopen later this year with an all-new design plus enhanced treatments and experiences ... More
22 Apr 2024
Following three disrupted lockdown years, the European fitness market bounced back in 2023, according to Deloitte and EuropeActive’s hot off the press European Health & ... More
21 Apr 2024
Charitable trust, Mytime Active, has removed all single-use plastic overshoes from its swimming pools and leisure centres, as part of ongoing sustainability efforts. Across the ... More
21 Apr 2024
Community Leisure UK is helping the drive to Net Zero with the launch of a bespoke carbon literacy course. Offered in partnership with the Workers' ... More
20 Apr 2024
Operator Circadian Trust has launched a five-year growth drive designed to support health and wellbeing across South Gloucestershire, UK. The initiative will see a £2.4m ... More
19 Apr 2024
Norwegian health club operator, Treningshelse Holding, which owns the Aktiv365 and Family Sports Club fitness chains, has acquired fellow Norwegian operator, Aktiv Trening. The purchase ... More
19 Apr 2024
The HCM team were busy at the recent FIBO Global Fitness event in Cologne, Germany, distributing a special FIBO edition of HCM in support of ... More
18 Apr 2024
Atlanta-based boutique fitness software company, Xplor Mariana Tek, has kicked off a push for international expansion. Shannon Tracey, VP of sales and marketing, says the ... More
1 - 15 of 67,887
The Leisure Media Company Ltd
The Leisure Media Company Ltd