Rio 2016 Olympic Park declared ‘92 per cent complete’

Construction work at Barra Olympic Park, the main competition cluster for the Rio 2016 Olympics, is now 92 per cent complete.

In its latest update on building progress, Rio de Janeiro’s city government announced that 12 venues across the two main Olympic Parks – Barra and Deodoro – are now “nearly complete”, compared with six venues last month (September 2015).

In Barra, finishing touches are being made to the athletes’ village (97 per cent), Olympic Aquatics Centre (94 per cent complete) and Future Arena (96 per cent), while work is still needed on the Olympic Tennis Centre (80 per cent) and the Rio Olympic Velodrome (70 per cent).

For a video animation on the progress made at Barra, click here.

Work is also progressing well at Deodoro Olympic Park, the second largest competition cluster, where work on two venues – the BMX and mountain bike courses – is complete.

When complete, the Olympic Park – masterplanned by AECOM – will be a lagoon-side peninsula with a network of 15 sports venues.

Located in the Barra da Tijuca district, the main Olympic park will be anchored around three existing stadiums, used for the 2007 Pan-American Games, which were constructed over a Formula One racetrack from the 1970s.

Seven new stadiums will be constructed on the site. These include a new handball arena, designed by London studio AndArchitects in collaboration with Rio-based Lopes, Santos & Ferreira Gomes; and a Velodrome, designed by 3DReid in partnership with local form BLAC Architects.

The opening ceremony of the Rio 2016 Games will take place on 5 August and the event will run until 21 August.

For more details on the Rio Olympic Parks and facilities, click here for the venues map for Rio 2016.

• The progress will come as a relief to the International Olympic Committee (IOC). In April 2014, IOC vice president John Coates described the preparations for the 2016 Games as “the worst ever seen”.

He said progress on the Rio’s infrastructure and venues – with two years to go at the time – was worse than it was for the Athens Games in 2004, which was notorious for delays in construction.

Sign up for FREE ezines & magazines
Construction work at Barra Olympic Park, the main competition cluster for the Rio 2016 Olympics, is now 92 per cent complete.
CLD,SAR,PRO,ARC,DES,EVT
845645_459926.jpg

More News

1 - 15 of 69,578
03 Jun 2026
Four Seasons Resort The Nam Hai in Hoi An, Vietnam, has put together a Global Wellness Day (GWD) agenda with activations rooted in nature and ... More
03 Jun 2026
Lithuanian care operator Addere Care has launched a “wellness care hospital” in Vilnius. It's the company’s second Lithuanian site, following a hospital in Trakai, but ... More
03 Jun 2026
Australia’s fast-growing fitness network, Viva Leisure, is adding a low-cost gym brand to its already extensive portfolio. The Zoo Fit rollout starts  in July with ... More
03 Jun 2026
Speedflex has launched a strength training programme for 10 to 16-year-olds, to make it safer, more inclusive and more engaging. Built on the Speedflex training ... More
01 Jun 2026
Tewinbury Farm Hotel in Hertfordshire, UK is expanding its premium leisure proposition with the launch of Farm Club, on 15 June. Located 30 minutes from ... More
01 Jun 2026

Work is underway in Madrid on one of Europe’s most significant multi-functional complexes, combining sport, entertainment, culture and education.

The €800 ... More

01 Jun 2026
Rainer Maelzer, an experiential entertainment innovator, has been appointed chief entertainment officer by Therme Group.  With decades of experience in immersive water-based attractions, Maelzer will ... More
29 May 2026
PureGym is encouraging people to step away from their screens and go for a walk, in a new initiative timed to coincide with Mental Health ... More
29 May 2026
Small improvements to sleep, diet quality, and physical activity, made in combination lead to a significantly reduced risk of major cardiovascular events, including heart attacks ... More
29 May 2026

Movie Park Germany has opened a new Paramount Pictures-themed attraction as part of its 30th anniversary celebrations, using immersive storytelling and adaptive reuse ... More

28 May 2026
The Global Wellness Summit (GWS) will celebrate its 20th anniversary at the 2026 event in Phuket, Thailand, later this year with the theme: The Science, ... More
28 May 2026
Auko, an all-inclusive development, is opening in Phong Nha in Vietnam in Q3 2026, with a series of 30 tented eco-lodges and wellness hospitality operations ... More
28 May 2026
Therme Manchester’s 28-acre development, which will include interconnected glass pavilions that measure 65,000sq m, will be the largest bathing and wellbeing attraction in the world ... More
28 May 2026

Efteling has opened Hooghmoed, a new family drop tower designed to broaden the appeal of its recently launched Sirene Island themed area and ... More

28 May 2026
Naples Beach Club, a Four Seasons Resort, has opened a 2,800sq m spa called The Sanctuary, with the design and concept inspired by the Native ... More
1 - 15 of 69,578
Elevate Arena
Elevate Arena